JUURAKKO
SOLAR PARK
PROJECT DESCRIPTION
Solarigo built Finland's largest solar power park as part of the Juurakko hybrid park in 2022 - 2023. In Juurakko hybrid park 7wind turbines and 24,000 solar panels produce renewable energy using the same electricity network infrastructure. VSB Uusiutuva Energia Suomi Oy was responsible for the construction of the wind turbines.
The project's goal was to create a hybrid park concept, which could be replicated internationally. In addition to combining two different forms of production, the project included large-scale electricity storage, as well as testing of bi-facial solar panels in industrial electricity production. The production of the hybrid park is directed directly to the main electricity grid. The park's solar energy is supplied to end users by Lumme Energia. The Ministry of Economic Affairs and Employment granted an energy subsidy of 2.6 million euros for the project.
PANELS
24,000
INVESTMENT M€
~ 8.7
STEP
PRODUCTION
LOCATION
KALAJOKI
CAPACITY MWP
13
Add a Title
Lorem ipsum
Add a Title
Lorem ipsum
Development
Solarigo and VSB Uusiutuva Energia Suomi Oy started negotiations on cooperation to build a wind-solar hybrid park. The construction of the wind turbines already started at the end of 2021, when Solarigo visited VSB in the area and the possible construction site of the solar park.
H2 / 2021
H2 / 2021
PROGRESS OF THE PROJECT
Agreement
Solarigo Systems Oy and wind power project developer VSB Uusiutuva Energia Suomi Oy signed an agreement to build Finland's first industrial-scale wind-solar hybrid power park in Kalajoki. At the time the project started, there were only a few similar hybrid parks in the world.
Both the wind and solar parks make use of the same substation, Fingrid Oyj's Kalajoki substation.
10 / 2021
10 / 2021
Design and planning
Site preparation began in the spring of 2022 with the construction and strengthening of roads, land transfering and fencing of the solar park. Also medium voltage cabling between the solar power plant and the wind turbine was built.
In the summer, the cables were dug under the field of the solar power plant. The main components such as solar panels, racks and inverters were delivered to the area for installation starting in the fall.
03 / 2022
03 / 2022
Production
The production of the Juurako solar park started in February 2023 when the first inverters were switched on.
02 / 2023
02 / 2023
Construction
Installation of power electronics started in September 2022.
09 / 2022
09 / 2022
Opening event
The opening of the Juurakko Solar Park was celebrated in August 2023. At the event, speeches were heard and the park was introduced for invited guests.
05 / 2022
08 / 2023
05 / 2022
Opening
The opening of the Juurakko Solar Park was celebrated in August 2023. At the event, speeches were heard and the park was introduced.
08 / 2023
2019